PROJECT TITLE :
Agricultural Drainage Scheme, Mukim
Jeram Batu, Pontian, Johore, Malaysia
CLIENT :
Department of Irrigation & Drainage,
Johore, Malaysia
DURATION :
September 1992 - May 1993
PROJECT DESCRIPTION
The design of tidal control gates, creek closures, levee,
collector drains, internal secondary drains, farm roads,
bridges and gate-keeper quarters for flood protection of
agricultural land. The application of MIKE11 for testing
various design alternatives, especially for unsteady tidal
control gate hydraulics.
PROJECT TITLE :
Hydraulic Study for Tg. Tokong Land
Reclamation, Penang, Malaysia
CLIENT :
Pengurusan Lebuhraya Bhd.
DURATION :
October 1992 - February 1993
PROJECT DESCRIPTION
The use of MIKE21 modelling software to determine the best
reclamation layout (between conventional and island systems of
reclamation) which includes the provision of a breakwater
system for about 980 acres of land on the northeastern part of
Penang. Movement of suspended particles within the vicinity of
the project area was also modelled.
PROJECT TITLE :
Environmental Impact Assessment (EIA)
& Design for Perlis Land Reclamation,
Perlis, Malaysia
CLIENT :
Perlis Land Sdn. Bhd.
DURATION :
October 1992 - December 1992
PROJECT DESCRIPTION
The preparation of an EIA report for the proposed 500 acres
reclamation within the Straits of Malacca near Kuala Perlis
which included hydraulic modelling. The design of the offshore
land reclamation which includes fill material, soil
improvement, coastal protection, drainage and soil
investigation was also carried out.
PROJECT TITLE :
Feasibility Study for Reclamation
Works at the Federal Territory of
Labuan, Malaysia
CLIENT :
Public Works Department (JKR),
Malaysia
DURATION :
January 1993 - September 1993
PROJECT DESCRIPTION
The preparation of an EIA report and a hydraulic study for the
proposed reclamation of about 7000 acres of land on the
eastern and southern coasts of Labuan Island, the only
International Offshore Financial Centre in Malaysia. The
hydraulic report detailed a geotechnical assessment, flood
mitigation (using MIKE11), hydraulic modelling for optimum
reclamation layout and nearshore sediment transport utilising
the MIKE21 and LITPACK modelling software. The preliminary
design of coastal protection works for the reclamation was
also made.
PROJECT TITLE :
Local Plan Studies for Padang
Matsirat & Padang Lalang, Langkawi,
Kedah, Malaysia
CLIENT :
Town & Country Planning Department
(JPBD) - Northern Branch, Malaysia
DURATION :
January 1993 - August 1993
PROJECT DESCRIPTION
The assessment of the existing water supply and drainage
conditions and the recommendation of guidelines for future
development of both areas in Malaysia's premier tourist island
destination. Among the issues discussed, was the shortage of
water and limited reserves available for drainage channels.
PROJECT TITLE :
Hydraulic Study for the Straits of
Johore, Malaysian- Singapore Border
CLIENT :
Johore Coastal Development Sdn. Bhd.
DURATION :
February 1993 - March 1993
PROJECT DESCRIPTION
The use of MIKE21 to study the current pattern, sediment
movement and erosion/accretion before and after the land
reclamation on the western part of the Malaysian side of the
causeway at Johor Bahru, state capital of Johore.
PROJECT TITLE :
Hydraulic Study for the Lumut
Maritime Terminal, Perak, Malaysia
CLIENT :
PCO Constructors Sdn. Bhd.
DURATION :
April 1993 - June 1993
PROJECT DESCRIPTION
Utilisation of MIKE21 to evaluate the possible impacts of the
proposed dredging activities during the construction of the
marine terminal at Sg. Dinding and to optimise dredging
operations to minimize impact to the surrounding areas.
PROJECT TITLE :
Hydraulics & Coastal Engineering
Study for Labuan Marina Centre,
Federal Territory of Labuan, Malaysia
CLIENT :
Waterfront Group
DURATION :
May 1993 - June 1993
PROJECT DESCRIPTION
A hydraulic study conducted to determine the environmental
impact of the land reclamation cum marina development (on the
southern coast of Labuan) on the surrounding coastal
environment and to advise the client on the conceptual design
of coastal protection work necessary for the marina.
PROJECT TITLE :
Structural Plan Studies for Kuala
Langat & Part of Sepang District,
Selangor, Malaysia
CLIENT :
Town & Country Planning Department
(JPBD), Malaysia
DURATION :
May 1993 - August 1993
PROJECT DESCRIPTION
The assessment of the existing state of coastal erosion and
the appraisal of the anticipated impacts on the coastal areas
due to a proposed development plan as the area is located
close to the new Kuala Lumpur International Airport in Sepang.
Recommendations and guidelines on development within the
coastal zone were also made.
PROJECT TITLE :
esign & Supervision for the
Construction & Completion of the
Proposed Offshore Beacons for the
Submerged Breakwater's Marker off
Rantau Petronas, Kerteh, Terengganu,
Malaysia
CLIENT :
PETRONAS
DURATION :
July 1993 - September 1993
PROJECT DESCRIPTION
Design, preparation of contract documents and supervision
during construction of the offshore beacons placed to warn
marine vessels of the presence of submerged breakwaters which
were built to protect the shoreline where a petroleum complex
is located.
PROJECT TITLE :
Hydraulic Study for the Proposed
Waterfront Mixed Development on Lot
650, Block 10, at Upper Lanang Road,
Sibu, Sarawak, Malaysia
CLIENT :
Rimbunan Hijau Sdn. Bhd.
DURATION :
July 1993 - August 1993
PROJECT DESCRIPTION
A study on current pattern and sedimentation, before, during
and after reclamation, conducted to determine the effects of
land reclamation as part of a mixed development on the banks
of the Rajang River.
PROJECT TITLE :
Flood Alleviation Study at km10 of
the New Klang Valley Expressway
(NKVE), Selangor, Malaysia
CLIENT :
Projek Lebuhraya Utara Selatan (PLUS)
Bhd.
DURATION :
August 1993 - April 1994
PROJECT DESCRIPTION
An investigation into the causes of flood occurrence on this
stretch of highway which has become an important link between
Kuala Lumpur and Shah Alam. Mitigation measures were proposed
and supervised by the consultant eg. the excavation of the
Damansara River channel flowing under one of the highway's
bridges just upstream of the affected area.
PROJECT TITLE :
Perak-Selangor Water Supply
Privatisation Project Feasibility
Study, Malaysia
CLIENT :
Renong Berhad
DURATION :
August 1993 - September 1993
PROJECT DESCRIPTION
A study was made of the commercial viability of initiating a
water supply privatisation package that takes into account the
immediate and future needs of both the states of Selangor and
Perak.
PROJECT TITLE :
Numerical Modelling for the Sg.
Sarawak Regulation Scheme, Sarawak,
Malaysia
CLIENT :
PPES Road Construction Sdn. Bhd. &
the Sarawak State Government
DURATION :
August 1993 - December 1993
PROJECT DESCRIPTION
It was envisioned by the state government that a barrage be
constructed to regulate the flow of the Sarawak River at all
times. The study was divided into several stages to achieve
adequate modelling of the hydraulics, sediment transport and
water quality in the Sarawak River. MIKE11 was used to assist
in the detailed design, flood forecasting and environmental
assessment of the river system and regulation scheme. MIKE21
was utilised to provide the current pattern for different
scenarios to aid navigation simulations conducted by the
client.
PROJECT TITLE :
Hydraulic Study for the Proposed
Sutera Harbour Land Reclamation,
Sabah, Malaysia
CLIENT :
Pembinaan OCK (M) Sdn. Bhd.
DURATION :
September 1993 - November 1993
PROJECT DESCRIPTION
A hydraulic study was initiated to investigate current
patterns, sediment movement and wave refraction activity
before and after the implementation of the proposed
reclamation facing the South China Sea. The reclamation which
is about 380 acres, a resort, residential and marina
development is situated approximately 2.5 km from the main
port of Kota Kinabalu.
PROJECT TITLE :
Hydraulic Study for Sand Mining at
Ramunia Shoals, Offshore Johore,
Malaysia
CLIENT :
Alur Jaya Sdn. Bhd. & Obayashi-Toyo
Joint Venture
DURATION :
September 1993 - November 1993
PROJECT DESCRIPTION
A company obtained a concession to extract high quality sand
about 50 km offshore from Johore's eastern coast. MIKE21 was
used to predict variation in current pattern, sediment
movement and wave activity at the shoreline due to the sand
mining activity.
PROJECT TITLE :
Consultancy Services for the Water
Supply Works at Southbound Nilai
Layby, Negeri Sembilan, Malaysia
CLIENT :
Project Lebuhraya Utara-Selatan
(PLUS) Bhd.
DURATION :
August 1993 - October 1995
PROJECT DESCRIPTION
Studied the demand and existing water supply to ascertain the
cause(s) of shortage during peak hours at the layby. Design
and implemetation of remedial measures such as piped
Department of Water Supply (JBA), pumps and water tanks were
executed.
PROJECT TITLE :
Drainage Master Plan Study for Batu
Pahat, Johore, Malaysia
CLIENT :
Department of Irrigation & Drainage ,
Malaysia
DURATION :
October 1993 - Present
PROJECT DESCRIPTION
Assessment of the existing hydrologic and hydraulic conditions
in Batu Pahat. The application of RAFTS-XP and MIKE11 in the
formulation of the conceptual and preliminary designs to
improve the town's drainage system.
PROJECT TITLE :
Hydraulic Study for the Malaysian-
Singapore Second Bridge, Malaysian-
Singapore Border
CLIENT :
Lintasan Kedua (LINK) Sdn. Bhd.
DURATION :
October 1993 - April 1995
PROJECT DESCRIPTION
It was proposed that a bridge be built as a second road link
between Malaysia and Singapore at Gelang Patah, Johore
(Malaysian side). MIKE21 was used to model the current pattern
and sediment movement for various scenarios which include the
provision of artificial islands. The model was also used to
evaluate scouring effects around the bridge piers.
PROJECT TITLE :
Leachate Dispersion Study for the
Development of a Sanitary Landfill
Site at Pulau Burong, Seberang Perai,
Penang, Malaysia
CLIENT :
Ranhill Bersekutu Sdn. Bhd.
DURATION :
October 1993 - January 1994
PROJECT DESCRIPTION
The site is located close to the coast near to the Penang-
Perak state border; an understanding of the current pattern
around the site is imperative so as to determine the extent of
dispersion of pollutants from the proposed landfill site to
the surrounding waters.
PROJECT TITLE :
Hydraulic Study for the Proposed
Development of Miri Resort City,
Sarawak, Malaysia
CLIENT :
Samling Corporation Sdn. Bhd.
DURATION :
December 1993 - March 1994
PROJECT DESCRIPTION
A study into the coastal processes and sediment movement in
determining the feasibility of performing a large scale land
reclamation which includes the diversion of the Miri River
utilising MIKE21 and LITPACK. The reclamation (which includes
a marina) is part of a residential cum resort development to
transform Miri town into a resort city by the next century.
The proposed drainage system for the urban and coastal
development is simulated via MIKE11 to assess its adequacy in
catering for major storms.
PROJECT TITLE :
Hydraulic Study for Sand Mining
Offshore Johore, Malaysia
CLIENT :
Golden Bake Sdn. Bhd.
DURATION :
November 1993 - December 1993
PROJECT DESCRIPTION
The client obtained a concession to mine high grade sand close
to the Ramunia Shoals, offshore Johore. MIKE21 was used to
determine current pattern before and after the sand mining and
sediment dispersion during the sand extraction.
PROJECT TITLE :
Design & Supervision for the
Integrated Shrimp Farm Project -
Construction of Jetty & Flume
Structure, Kerpan, Kedah, Malaysia
CLIENT :
Samak Aquaculture Sdn. Bhd.
DURATION :
1994 - Present
PROJECT DESCRIPTION
Design of a jetty and flume structure for conveyance of
seawater 2 km offshore pumped at regular intervals daily to
the shrimp farm inland which is located close to Alor Setar,
state capital of Kedah. HYDEC also supervised the construction
of the structure.
PROJECT TITLE :
Hydraulic Study for Dredging off the
Coast of Johore, Malaysia
CLIENT :
Ranhill Bersekutu Sdn. Bhd. on behalf
of Sime Sembawang Sdn. Bhd.
DURATION :
January 1994 - February 1994
PROJECT DESCRIPTION
As part of its expansion plans, a shipyard on the southern
coast of Johore intends to deepen the waters fronting the
shipyard. MIKE21 was used to determine the effects of such
deepening on the surrounding area.
PROJECT TITLE :
Numerical Modelling for Coastal
Protection & Land Reclamation at
Brighton Beach, Miri, Sarawak,
Malaysia
CLIENT :
Doyon Development Sdn. Bhd.
DURATION :
January 1994 - February 1994
PROJECT DESCRIPTION
The client intends to reclaim a small portion of land in front
of an existing 4-star hotel. Thus a study of the effects of
such activity on the nearshore hydraulic regime was conducted.
PROJECT TITLE :
Hydraulic Study for the Proposed
Deepwater Port Development at Senari,
Sarawak, Malaysia
CLIENT :
U.P. Services Sdn. Bhd.
DURATION :
February 1994 - March 1994
PROJECT DESCRIPTION
The development of a new port for Kuching, state capital of
Sarawak, on the banks of the Sarawak River was studied using
MIKE21 to assess the effects of the development to the
riverine hydraulic regime.
PROJECT TITLE :
A Study for the Development of Marine
Pollution Control Regulations,
Malaysia
CLIENT :
Department of Environment, Malaysia
DURATION :
February 1994 - December 1994
PROJECT DESCRIPTION
Malaysia's coastal waters have some of the world's richest
ecosystems and habitats supporting a wide diversity of marine
life and providing valuable resources. The study was carried
out to evaluate the present extent of marine pollution;
examine existing legislation and regulations; review current
and available treatment technologies; review the existing
institutional framework and recommend measures and provisions
for the effective control of marine pollution.
PROJECT TITLE :
Combined Cycle Power Plant Project at
Lumut, Perak, Malaysia
CLIENT :
Sikap Energy Ventures Sdn. Bhd.
DURATION :
February 1994 - January 1995
PROJECT DESCRIPTION
Cooling water intake and outlet pipelines are to be installed
for the power plant. For the purpose of detailing the layout
of the intake and outlet works, studies were performed
regarding nearshore bathymetry, hydrodynamic conditions, sea
water conditions, rate of recirculation and soil conditions.
PROJECT TITLE :
Numerical Modelling Study for Pantai
Kok, Langkawi Island, Malaysia
CLIENT :
Berjaya Langkawi Beach Resort Sdn.
Bhd.
DURATION :
April 1994 - August 1994
PROJECT DESCRIPTION
To cater for the rising influx of tourists to Langkawi Island,
the client wishes to develop a golf course and an inland
marina next to its existing resort (which also includes the
construction of a training wall for beach stabilisation and
wave dissipation). MIKE21 was utilised to model the current
pattern and sediment movement in the vicinity of Pantai Kok's
nearshore area. The model was also used to model flushing
effects and the movement of pollutants within the marina.
PROJECT TITLE :
Langkawi Marina Project - Hydraulic
Study, Kedah, Malaysia
CLIENT :
Coastal & Offshore Engineering
Institute, Universiti Teknologi
Malaysia on behalf of EKRAN Berhad
DURATION :
April 1994 - June 1995
PROJECT DESCRIPTION
The client has proposed an approximately 2000 hectares'
reclamation project on the west coast of Langkawi which
incorporates the Langkawi airport runway extension, a golf
course, resort and marina development. A hydraulic study was
conducted to determine the best reclamation layout for the
least disturbance to the hydraulic regime of the surrounding
area.
PROJECT TITLE :
EIA for the Proposed Beach Resort on
Lot 141, 142, 144 & 146 Batu Rakit,
Kuala Terengganu for Sutera Beach
Resort, Terengganu, Malaysia
CLIENT :
Priced Resources Sdn. Bhd.
DURATION :
April 1994 - August 1994
PROJECT DESCRIPTION
An EIA study was conducted for a 9.73 acres' seafront resort
development situated about 27 km from Kuala Terengganu, state
capital of Terengganu. As the resort complex was located close
to the beach, the provision of a coastal protection measure
was recommended.
PROJECT TITLE :
Detailed Design for Improvement of
Parit Dhoby, Batu Pahat, Johore,
Malayisa
CLIENT :
Department of Irrigation & Drainage,
Malaysia
DURATION :
May 1994 - May 1995
PROJECT DESCRIPTION
The existing Parit Dhoby, an irrigation and drainage channel
which drains into the Batu Pahat River, floods regularly due
to a reduction in its conveyance and flow capacity. A design
of the improvement of the drain and related structures, such
as tidal gates to prevent flooding influenced by tides from
the river, was executed.
PROJECT TITLE :
EIA & Hydraulic Study for the
Proposed Integrated Resort
Development at Tg. Rhu in Langkawi
Island, Kedah, Malaysia
CLIENT :
Kauthar Venture Capital Sdn. Bhd.
DURATION :
May 1994 - September 1994
PROJECT DESCRIPTION
Tg. Rhu, with its sandy beaches and clear blue water, is
situated on the northern coast of Langkawi Island. It is at
this location that a resort, marina and residential
development is proposed. An EIA study was conducted for this
purpose. A hydraulic study was done to study the current
pattern, wave activity and sediment movement within the
vicinity of the project area, before, during and after
development. MIKE21 was also used to study the placement of
offshore breakwaters and the construction of a marina at the
Rhu River estuary. A separate study was also conducted to
identify the flora and fauna of the wetlands in the immediate
vicinity of the project area.
PROJECT TITLE :
Hydraulic Study for the Proposed
Fishing Harbour at Batu Maung, Pulau
Pinang, Malaysia
CLIENT :
Jurutera Konsultan (SEM) Sdn. Bhd.
DURATION :
July 1994 - May 1996
PROJECT DESCRIPTION
As a fishing port situated on the southeastern part of Pulau
Pinang, Batu Maung has over the years catered for an
increasing number of fishermen and their vessels. To remedy
the current congestion at the port, the government has
proposed that the part of the waters within the port area be
deepened and new jetties be built. A breakwater system is also
proposed by the main consultant of this project to provide
better shelter for the fishermen. The wave activity and
current pattern around the area was modelled using MIKE21. A
large scale field data collection programme was prepared by
HYDEC and executed by a client appointed licenced surveyor.
PROJECT TITLE :
Sedimentation Study for a Collapsible
Weir on Sg. Sarawak Kiri, Sarawak,
Malaysia
CLIENT :
Syed Muhammad, Hooi & Binnie Sdn.
Bhd. & the Kuching Water Board
DURATION :
August 1994 - November 1994
PROJECT DESCRIPTION
The sediment transport behaviour in the Sarawak Kiri River, in
relation to the existing and post barrage conditions, was
studied. This behaviour determined the impact of sedimentation
on the collapsible weir proposed for water supply intake.
PROJECT TITLE :
Hydraulic Study for the Reclamation
of Pulau Sekati at Kuala Terengganu,
Malaysia
CLIENT :
Department of Irrigation & Drainage,
Terengganu, Malaysia
DURATION :
August 1994 - June 1996
PROJECT DESCRIPTION
Pulau Sekati is an island located within the Terengganu River
estuary. The construction of a link such as a bridge or
causeway or total or partial reclamation of the channel
between the island and the right bank of Terengganu River was
proposed. A large scale field data collection programme was
prepared and executed jointly between HYDEC and the client.
MIKE11 was utilised to assess flooding conditions due to the
various alternatives. MIKE21 was used to determine the best
reclamation layout with respect to the hydraulic regime in the
immediate vicinity.
PROJECT TITLE :
Hydraulic Study for Chendering
Fishing Port, Terengganu, Malaysia
CLIENT :
Public Works Department (JKR),
Malaysia
DURATION :
July 1994 - May 1996
PROJECT DESCRIPTION
The Chendering fishing port is important to fishermen who not
only unload their catch but also moor their vessels there. Due
to the siltation of many of the rivermouths in Terengganu,
there has been an increasing number of fishermen using this
port which is accessible all year round. To accommodate the
increase, the authorities have decided to improve the port
facilities. A study was conducted to analyse a new breakwater
system and the effects of the existing breakwaters to the
surrounding areas. The study also included the analysis of
existing shoreline conditions, coastal processes and the
effectiveness of the existing breakwaters. Both the MIKE21 and
LITPACK modelling softwares were utilised.
PROJECT TITLE :
EIA for Bakun Hydro-Power Dam -
Downstream Hydrology and Hydraulics,
Sarawak, Malaysia
CLIENT :
Universiti Teknologi Malaysia on
behalf of Bakun Management Sdn. Bhd.
DURATION :
August 1994 - August 1995
PROJECT DESCRIPTION
The construction of the Bakun Hydroelectric Dam was to cater
for the power needs of the nation in the wake of rapid
development taking place. The dam is situated upstream of the
Rajang River, the longest river in Malaysia. A study of flood
and drought levels, sedimentation/erosion, as well as riverine
water quality was conducted using MIKE11. The occurance of
dambreak was modelled, using MIKE21, to determine the extent
and effects of onrushing water towards the towns located along
the river. A quantitative risk analysis report was also
submitted to the client.
PROJECT TITLE :
EIA for Cahaya, the Sanctuary, Shah
Alam, Selangor, Malaysia
CLIENT :
U.P. Services Sdn. Bhd.
DURATION :
September 1994 - October 1994
PROJECT DESCRIPTION
An EIA study was conducted for a proposed upmarket residential
project located on a hill not far from an agricultural park in
Shah Alam. Of particular concern was the presence of a stream
and its water quality within the project location.
PROJECT TITLE :
Hydraulic Study for Dumpil Bay Resort
Development, Sabah, Malaysia
CLIENT :
Sabah Urban Development Corporation
Sdn. Bhd.
DURATION :
September 1994 - July 1995
PROJECT DESCRIPTION
Modelling work using MIKE21 was carried out to study the
effects of development (which includes reclamation, diversion
channels and a marina) situated slightly south of Kota
Kinabalu. Of particular importance was the current pattern,
nearshore wave activity and sediment movement in the vicinity
of the project area.
PROJECT TITLE :
Hydraulic Study of the Proposed
Coastal Road from Teluk Chempedak to
Beserah, Pahang, Malaysia
CLIENT :
Public Works Department (JKR),
Malaysia
DURATION :
October 1994 - September 1995
PROJECT DESCRIPTION
A road linking Teluk Chempedak, a popular beach in Pahang and
Beserah situated close to Kuantan, the state capital of Pahang
was proposed to provide access to the public. The proposed
road crosses the Beserah River several times. The MIKE11
modelling study determines the impacts of the road on the
catchment hydrology and river hydrodynamics.
PROJECT TITLE :
Hydraulic Analysis of River Crossings
for Gas Pipeline in Kluang, Johore,
Malaysia
CLIENT :
MMC Engineering Sdn. Bhd.
DURATION :
October 1994 - February 1995
PROJECT DESCRIPTION
The client proposed the construction of a gas pipeline that
crosses three rivers in Kluang. The study identified the 50-
and 100-year flood levels to fulfill the Department of
Irrigation and Drainage's requirements as well as obtaining
the optimum pipe burying depth.
PROJECT TITLE :
Coastal Erosion/Accretion Studies for
the Proposed Land Reclamation Works
Along the Malacca Coast, Malacca,
Malaysia
CLIENT :
Olympia Land Bhd.
DURATION :
December 1994 - February 1995
PROJECT DESCRIPTION
A 353 acres' land reclamation project fronting the Portuguese
Settlement on the outskirts of Malacca City was proposed. The
MIKE21 modelling work included assessment of the reclamation
to the current pattern, sediment movement and nearshore wave
activity.
PROJECT TITLE :
EIA for the Proposed Commercial &
Housing Development of 130 Acres of
Land at Sembulan Renewal Scheme,
Phase 4 & 5, Sabah, Malaysia
CLIENT :
Skylark Jaya Sdn. Bhd.
DURATION :
March 1995 - October 1995
PROJECT DESCRIPTION
An EIA study was conducted to facilitate a land reclamation
next to Tg. Aru, slightly south of Kota Kinabalu. A study into
locating the source of fill material was also conducted around
the reclamation site. The effects of reclamation and dredging
(for fill material) onto the surrounding shoreline, including
the newly developed Sutera Harbour reclamation adjacent to it,
was modelled using MIKE21.
PROJECT TITLE :
Hydraulic Study for the Proposed
D'Ambang Kota Resort Township at
Mukim Jimah, District of Port
Dickson, Negeri Sembilan, Malaysia
CLIENT :
True Creation Sdn. Bhd.
DURATION :
April 1995 - September 1995
PROJECT DESCRIPTION
As part of the proposed mixed development in Lukut, part of
the Lukut River would be reclaimed with dredging carried out
at certain locations around the river to construct waterfront
housing. The river was modelled via MIKE11 and MIKE21 to
ascertain the effects on river dynamics and sediment transport
due to the proposed development.
PROJECT TITLE :
Hydraulic Study for the Proposed
Sembilan Marine Resort Development,
Negeri Sembilan, Malaysia
CLIENT :
Sembilan Marine Resort Sdn. Bhd.
DURATION :
April 1995 - February 1995
PROJECT DESCRIPTION
Located near the Linggi River estuary, the client proposed a
mixed-type development (with a marina club) by reclaiming part
of the existing mangrove swamp. MIKE21 was used to model the
current patterns and nearshore wave activity.
PROJECT TITLE :
Hydraulic Study for the Proposed
Riverfront Resort Tourist Development
at Tg. Agas, Johore, Malaysia
CLIENT :
KEJORA & Mustika Sakti Sdn. Bhd.
DURATION :
May 1995 - September 1995
PROJECT DESCRIPTION
MIKE21 was utilised to assess the viability of initiating a
resort development, centered around the Tg. Belungkor jetty
(near the entrance of the Johore River) to cater for the
influx of tourists from Singapore and Bintan, Indonesia, by
reclaiming part of the mangrove swamps. Apart from current
patterns, nearshore wave activity and sediment movement, a
study of the prominence of streams and tributaries within the
project area was also made.
PROJECT TITLE :
Hydraulic Study for a Mixed
Development on Reclaimed Land of an
Area 528 Acres in Umbai, Malacca,
Malaysia
CLIENT :
KUB Development Bhd.
DURATION :
July 1995 - October 1995
PROJECT DESCRIPTION
Located fronting Pulau Besar in Malacca, the reclamation which
includes a marina, is conceived to bring in tourists. MIKE21
was used to study the current pattern and nearshore wave
activity before and after reclamation. Sediment movement
during the reclamation process was also modelled.
PROJECT TITLE :
Consultancy Services for the Proposed
Integrated National Primary School at
Kuala Kangkong, Daerah Kota Setar,
Kedah, Malaysia
CLIENT :
Kauthar Sdn. Bhd.
DURATION :
September 1995 - Present
PROJECT DESCRIPTION
The preparation of land survey and soil investigation
specifications, design and related engineering works for the
construction of an integrated primary school in Kedah.
PROJECT TITLE :
Hydraulic Study for Labuan Integrated
Jetty Masterplan, Federal Territory
of Labuan, Malaysia
CLIENT :
Pengurusan Lantas Sdn. Bhd.
DURATION :
October 1995 - March 1996
PROJECT DESCRIPTION
The client undertook a feasibility study of marine related
works in Labuan. Using MIKE21, impacts (current pattern, wave
penetration and siltation) of the proposed reclamation and
breakwater installation were studied.
PROJECT TITLE :
Hydraulic Study for the Tioman Beach
Improvement & Marina Works, Tioman
Island, Pahang, Malaysia
CLIENT :
Berjaya Tioman Beach Resort Sdn. Bhd.
DURATION :
October 1995 - February 1995
PROJECT DESCRIPTION
Located on the southwestern part of Tioman Island, the Berjaya
Tioman Beach Resort is currently facing acute shore retreat
problems which is being remedied temporarily by beach
nourishment. MIKE21 was used to study the best location to
place offshore breakwaters and artificial breakwaters as well
as studying the effects of providing river training
breakwaters at the mouths of rivers/streams which have their
outlets within the resort grounds. MIKE21 was also used to
assess the placement of a breakwater system for a marina
located immediately south of the existing resort.
PROJECT TITLE :
Hydraulic Study for Shipyard
Activities at Teluk Gong, Mukim
Kelang, Selangor, Malaysia
CLIENT :
Muhibbah Marine Engineering Sdn. Bhd.
DURATION :
November 1995 - Present
PROJECT DESCRIPTION
It is the intention of the client to provide shipyard
facilities within the Kelang River (slightly south of South
Port) near the bridge linking Teluk Gong and West Port. MIKE21
was used to study the current pattern as well as the
sedimentation rate and sediment movement around the project
area.
PROJECT TITLE :
Pekan Rompin Structure Plan Study,
Pahang, Malaysia
CLIENT :
State Economic Planning Unit (UPEN),
Pahang
DURATION :
February 1996 - Present
PROJECT DESCRIPTION
In order to map out future development strategies for the
Pekan-Rompin district, a structure plan study was initiated.
Among the issues raised was drainage and flood mitigation
which includes assessment of the existing conditions, current
related problems and erosion.
PROJECT TITLE :
Hydraulic Study & Soil Investigation
Works for Sayak Beach & Country
Resort Development in Mukim Kuala
Muda, Kedah, Malaysia
CLIENT :
Sayak Beach & Country Resort Sdn.
Bhd.
DURATION :
November 1995 - March 1996
PROJECT DESCRIPTION
MIKE21 was used to analyse the effects to the hydraulic regime
of a proposed mixed-type development on approximately 5000
acres of reclaimed seafront land located near the Kedah-Penang
border. Apart from modelling the sediment movement during
reclamation works, sediment discharge of the Muda River and
the placement of offshore discharge outlets were also modelled
using MIKE21.
PROJECT TITLE :
langor Tourism Master Plan & Action
Plan Study, Selangor, Malaysia
CLIENT :
Town & Country Planning Department
(JPBD), Malaysia
DURATION :
November 1995 - May 1996
PROJECT DESCRIPTION
The study, which is multi-disciplinary and comprehensive, will
address the future touristic development of Selangor. Among
its objectives is the study of the drainage system and coastal
area management system.
PROJECT TITLE :
lydraulic Study for the Proposed
Resort Development on a Portion of
Lot 305, Mukim Si Rusa, Port Dickson,
Negeri Sembilan, Malaysia
CLIENT :
Fortune Valley Sdn. Bhd.
DURATION :
December 1995 - February 1996
PROJECT DESCRIPTION
The client proposed to develop a stretch of beach into a
resort complex in Port Dickson, a popular tourist destination.
Part of the resort would be in the form of chalets built on
piles. A study was conducted to assess the effects of the
piles' placement to the nearshore coastal processes utilising
MIKE21 and LITPACK.
PROJECT TITLE :
Coastal & Marine Studies for the
Development of Pulau Rebak Besar,
Mukim Kedawang, Langkawi Island,
Malaysia
CLIENT :
Rebak Island Marina Berhad
DURATION :
December 1995 - March 1996
PROJECT DESCRIPTION
Pulau Rebak Besar, an island located southwest of Langkawi,
has been earmarked for tourism development. The island has one
of the most sheltered marinas in Langkawi. It was necessary to
conduct a marine resource inventory survey in the vicinity of
the island's waters. A study into the coastal processes and
sediment movement was made to ascertain the impacts of
development. The study also included assessment of navigation
and conditions within the completed marina basin. Locations
for jetties on the island and on Langkawi were also selected
based on wave activity and nearshore bathymetry.
PROJECT TITLE :
EIA for the Proposed 145 Acres
Sembilan Marine Resort Mixed
Development at Tg. Agas, Mukim Pasir
Panjang, Port Dickson, Negeri
Sembilan, Malaysia
CLIENT :
Sembilan Marine Resort Sdn. Bhd.
DURATION :
January 1996 - March 1996
PROJECT DESCRIPTION
An EIA study was conducted for the proposed mixed development
on reclaimed mangrove swamps located next to the Linggi River
estuary. Of particular concern was the water quality in the
vicinity of the project area.
PROJECT TITLE :
Golok Rivermouth Improvement Project,
Tumpat, Kelantan, Malaysia
CLIENT :
Department of Irrigation & Drainage,
Malaysia
DURATION :
January 1996 - Present
PROJECT DESCRIPTION
The Malaysian government intends to proceed with the
implementation of the project which includes the construction
of a rubble mound breakwater, a rip-rap revetment and a river
training groyne. The scope of consultancy services includes
the preparation of final contract documents and all related
aspects with regard to work supervision.
PROJECT TITLE :
Engineering Consultancy Services for
Tg. Rhu Development, Langkawi Island,
Kedah, Malaysia
CLIENT :
Kauthar Sdn. Bhd.
DURATION :
February 1996 - Present
PROJECT DESCRIPTION
Advising the client on the hydrologic and hydraulic behaviour
of the Tg. Rhu area and the impacts of various proposed
developments on the surroundings. Also, the design of various
structures around Radisson Tg. Rhu, an exclusive suite hotel.
PROJECT TITLE :
Hydraulic Study for the Proposed
Mixed Development at Sg. Terap, Batu
Gajah, Perak, Malaysia
CLIENT :
Urban Development Authority (UDA),
Malaysia
DURATION :
April 1996 - Present
PROJECT DESCRIPTION
The MIKE11 modelling of Johan River which flows through the
development site (ex-tin mining land situated next to the
Kinta River not far from Ipoh, state capital of Perak) to
assess the flooding situation around the area.
PROJECT TITLE :
Hydraulic Study for the Proposed
"Waterfront International Cities"
Development at Mukim Sg. Petani, Sg.
Panjang & Bujang District of Kuala
Muda, Kedah, Malaysia
CLIENT :
Endah Maju Sdn. Bhd.
DURATION :
May 1996 - Present
PROJECT DESCRIPTION
The client wishes to develop 2805 acres of mangrove wetlands.
MIKE11 modelling was carried out to ascertain the flooding
situation before and after development. The functions of the
mangrove wetland as a natural flood storage for Merbok River
and Petani River would also be determined.
PROJECT TITLE :
Preparation of an Environmental
Management Plan (EMP) for the
Proposed Beris Dam Project, Kedah,
Malaysia
CLIENT :
Department of Irrigation & Drainage,
Malaysia
DURATION :
May 1996 - Present
PROJECT DESCRIPTION
The EMP (which covers various topics such as biology, public
health, geotechnical engineering, etc.) includes the
application of dam-break modelling, GIS and the establishment
of a reservoir conservation and management plan.
PROJECT TITLE :
A Study into the Integrated Nature
Programme Development at Tg. Rhu,
Langkawi Island, Malaysia
CLIENT :
Kauthar Sdn. Bhd.
DURATION :
May 1996 - Present
PROJECT DESCRIPTION
The report will describe the important natural resources and
features, their locations, conservation status, origins, uses,
functions and other relevant information. The major topics
which would be covered are the flora & fauna, coastal & marine
resources and cultural & geological heritage.